QuestionQ74

Product

After three iterations, a project’s underlying security-structure architecture is found to be unstable. Although a technical solution exists, all work completed to date is flawed. This will affect several future business-service offerings.

What should the product owner do to resolve this?

  • A Ask the development team to address the issue since it is in their domain
  • B Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan
  • C Meet with the team and stakeholders to address rework and rewrite stories as needed
  • D Cancel the current sprint, and meet with stakeholders to reassess the project's validity
Explanation

A major architectural defect that invalidates completed work and affects future business services requires coordinated discussion with the team and stakeholders. The product backlog must reflect the necessary rework, including rewriting affected stories as needed.