ProductAfter three iterations, a project’s underlying security-structure architecture is found to be unstable. Although a technical solution exists, all work completed to date is flawed. This will affect several future business-service offerings.
What should the product owner do to resolve this?
- A Ask the development team to address the issue since it is in their domain
- B Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan
- C Meet with the team and stakeholders to address rework and rewrite stories as needed
- D Cancel the current sprint, and meet with stakeholders to reassess the project's validity