QuestionQ72
DeliveryDuring a project review, the team identifies customer feedback that would increase scope. The project leader is concerned that the team cannot incorporate this feedback and still meet the product launch date.
What should the project leader do?
- A Finalize the feedback in the form of a change request
- B Limit the scope of the feedback to only those changes that the team can feasibly accommodate
- C Encourage all feedback, then work with the customer to prioritize work for future sprints
- D Allow the team to decide what feedback to incorporate