How should a project leader manage stakeholder expectations on an agile project?

  • A Establish a common vision and success criteria and involve all the stakeholders in the iteration reviews
  • B Invite stakeholders for the iteration reviews but do not include new stakeholders which may limit project success
  • C Involve all the stakeholders in iteration reviews but do not entertain all expectations of all stakeholders
  • D Communicate issues to all stakeholders via email and only communicate risks to internal stakeholders
Explanation

A shared vision and agreed success criteria align stakeholder expectations, while involving stakeholders in iteration reviews provides regular transparency, feedback, and opportunities to adjust priorities as the work evolves.