QuestionQ51

VerifiedBusiness Continuity

An administrator operates two clusters: Site A and Site B. Async DR is configured between them as follows:

  • Site A is the Primary Site.
  • Site B is the inactive Secondary Site, with no VMs running.
  • Site A is fully in production.
  • Site B is used for backup/disaster recovery.

The customer wants to perform a planned failover between the sites. How should the administrator do this?

Explanation

For asynchronous DR, a planned failover is a controlled migration from the active primary site to the secondary recovery site. The Migrate action must be initiated on the active source, Site A; Activate is used to activate the secondary site for recovery rather than to perform the planned migration.