QuestionQ51

Business Continuity

An administrator operates two clusters: Site A and Site B. Async DR is configured between them as follows:

  • Site A is the Primary Site.
  • Site B is the inactive Secondary Site, with no VMs running.
  • Site A is fully in production.
  • Site B is used for backup/disaster recovery.

The customer wants to perform a planned failover between the sites. How should the administrator do this?

  • A Click Activate on the Secondary site within the Data Protection Dashboard
  • B Click Activate on the Secondary site and run deactive NCLI command on Primary site
  • C Choose Migrate on the Secondary site within the Data Protection Dashboard
  • D Choose Migrate on the Primary site within the Data Protection Dashboard
Explanation

For asynchronous DR, a planned failover is a controlled migration from the active primary site to the secondary recovery site. The Migrate action must be initiated on the active source, Site A; Activate is used to activate the secondary site for recovery rather than to perform the planned migration.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!