QuestionQ9

Problem Management

An organization has begun introducing problem management. It has identified and resolved some problems, and the problem manager now wants to expand the practice.

Which activity should the problem manager undertake NEXT?

  • A Document process workflows and activities for an increased problem management scope
  • B Configure the service management tool to ensure that problems and known errors can be managed throughout their lifecycle
  • C Talk to senior leadership about the benefits that have already been achieved, and the risks that could be addressed in future
  • D Engage with suppliers and partners to ensure that they actively participate in future problem management activities
Explanation

Expanding problem management requires senior-leadership sponsorship and support. Communicating the benefits already achieved and the future risks that proactive problem management can address establishes the value case for investment and broader adoption.