QuestionQ44

VerifiedChapter 4: Test Analysis and Design

At what point is a detailed risk analysis for a story initially performed?

Explanation

Detailed risk analysis occurs during iteration planning, when the delivery team plans an individual story at sufficient depth to assess its implementation uncertainties and risks. Project, release, and epic planning address risks at broader planning horizons.