QuestionQ44Verified/Chapter 4: Test Analysis and DesignCopy linkReport a problemAsk AstroTutorSave questionAt what point is a detailed risk analysis for a story initially performed?AProject planningBIteration planningCRelease planningDEpic planningShow AnswerAnswerExplanationDetailed risk analysis occurs during iteration planning, when the delivery team plans an individual story at sufficient depth to assess its implementation uncertainties and risks. Project, release, and epic planning address risks at broader planning horizons.Show comments1Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!