QuestionQ43
VerifiedChapter 1: Fundamentals of TestingYour organization’s test strategy specifies that using more than one method to estimate test effort is desirable. You are responsible for determining the test effort for the next project. Historical information shows that the project type being estimated has a development-to-test effort ratio of 5:3.
The initial development-effort estimate is 450 person-days.
Which ONE of the following options represents the estimated test effort when using the ratio-based method?