QuestionQ10

Process for Improvement

You are performing a TMMi assessment for a small organization. It recognizes that its internal processes are fairly chaotic, but wants to understand how far it is from TMMi level 2. Test design and execution and test environment have been designated out of scope because a third party manages and performs them. You have analyzed the scores for the in-scope areas, which are:

  • Test Policy and Strategy — fully achieved
  • Test Planning — partly achieved
  • Test Monitoring and Control — fully achieved
  • Test Design and Execution — not applicable
  • Test Environment — not applicable

What overall rating would you assign to the organization?

Explanation

A TMMi maturity-level rating is governed by the lowest rating among the applicable process areas. Process areas rated not applicable do not influence the assessment result. Because Test Planning is partly achieved and the other applicable areas are fully achieved, the overall rating is partly achieved.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!