QuestionQ10
Process for ImprovementYou are performing a TMMi assessment for a small organization. It recognizes that its internal processes are fairly chaotic, but wants to understand how far it is from TMMi level 2. Test design and execution and test environment have been designated out of scope because a third party manages and performs them. You have analyzed the scores for the in-scope areas, which are:
- Test Policy and Strategy — fully achieved
- Test Planning — partly achieved
- Test Monitoring and Control — fully achieved
- Test Design and Execution — not applicable
- Test Environment — not applicable
What overall rating would you assign to the organization?
Community Discussion