QuestionQ36

VerifiedRisk Response and Reporting

After new risk events have been identified during a project, what should the project manager do NEXT?

Explanation

Newly identified risks are documented in the risk register so their causes, potential impacts, ownership, and subsequent analysis or response planning can be tracked.