QuestionQ36

Risk Response and Reporting

After new risk events have been identified during a project, what should the project manager do NEXT?

  • A continue with a quantitative risk analysis
  • B determine if the scenarios need to be accepted or responded to
  • C continue with a qualitative risk analysis
  • D record the scenarios into the risk register
Explanation

Newly identified risks are documented in the risk register so their causes, potential impacts, ownership, and subsequent analysis or response planning can be tracked.