You are the project manager in your enterprise. You have identified that a risk event has occurred in your enterprise. You have preplanned risk responses. You have monitored the risks that occurred. What immediate step must be taken after this monitoring process in response to the risk events?

Explanation

When a risk event occurs, it becomes an issue or incident that requires execution of the applicable preplanned response. Incident response addresses the realized event immediately; risk-register updates and lessons learned follow as part of recording and improving risk management.