Present and demonstrate the solution to the customer and coordinate implementation planning
You are presenting an HPE Alletra 9000 solution to a customer. They request a high-level implementation checklist to prepare their site before implementation.
Which resource can you share with the customer to help provide this checklist?
AInfoSight Welcome Center
BData Services Cloud Console
CSmartCID
DSPOCK
0
Community Discussion
No comments yet. Be the first to start the discussion!
Recommend and position HPE offerings (solutions, products, and services) for customer use cases
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
0
Community Discussion
No comments yet. Be the first to start the discussion!
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
0
Community Discussion
No comments yet. Be the first to start the discussion!
A client requires a departmental storage array to host a VDI workload at a remote office. The networking infrastructure is limited, and the client has chosen to connect the ESXi host servers using 12 Gbps SAS.
Which HPE Storage product meets these requirements?
AHPE Alletra 9060
BHPE Nimble AF20
CHPE MSA 2062
DHPE Alletra 6030
Which components may be included in HPE’s disaggregated hyperconverged infrastructure (dHCI)?
Choose three
AHPE B-series switches
BHPE Alletra 6000 array with FC HBAs
CHPE ProLiant DX
DHPE Alletra 6000 array with iSCSI HBAs
EHPE Aruba switches
FHPE ProLiant DL
A customer is considering an HPE SAP HANA solution built on HPE SuperDome Flex and HPE Alletra 9000.
Which additional product should be offered?
AHPE GreenLake for Private Cloud Enterprise
BHPE Apollo 6500 Gen10 Plus
CHPE GreenLake for database
DHPE StoreOnce
What values does the TCO Calculator provide?
Choose two
AReturn on investment (ROI)
BCost to company (CTC)
CCapital expenditure (CAPEX)
DNet present value (NPV)
EOperational expenditure (OPEX)
A customer is experiencing substantial growth of large, high-priority data sets in its datacenter. The data is highly sensitive.
Which solution should be implemented, and why?
ATraditional, as it is the easiest solution to implement and scale for data growth.
BCloud, as it is the simplest solution and simplicity is best for security large data-sets.
CHybrid solutions, as they are most common in secure, high-priority implementations.
DTraditional, as it can be completely isolated from potential external threats.
You are planning a new data center solution for a customer that has a limited power footprint.
Which tools can you use to present the proposed solution’s power consumption to the customer?
Choose two
AOCA
BNinjaSTARS
CSSET
DProduct Bulletin
EPower Advisor
A customer requires an 8:1 GPU-to-CPU ratio for their natural language processing (NLP) application.
Which HPE platform fulfills this requirement?
AApollo 6500 Gen10 Plus
BSynergy SY480 Gen10 Plus with 8 Bay PCIe Expansion
CProLiant DL380 Gen10 Plus
DEdgeLine e910 Server Blades
A customer wants to add a backup component to the HPE GreenLake solution being prepared for them. Their primary requirements are cost-optimized backups, long-term data retention, and operational simplicity.
Which component should be added to their solution?
AHPE Backup and Recovery Service
BHPE Cloud Bank Storage
CCommvault
DZerto
Match each tool to its use category.
Drag & Drop
Data Collection
Data analysis and solution sizing
SAF Collector
SAF Analyse
NinjaSTARS
NinjaCrawler
DD Analyse
Compared with OCA, which extra datacenter characteristic is required to configure a solution in SSET?
AKW per rack
BCountry
CInput voltage
DInput phase
Under what circumstances should a customer be offered an HPE GreenLake Cloud Service trial?
AWhen the customer wants to evaluate a high-performance, large-scale power-user VDI cluster in the public cloud.
BWhen the customer wants to evaluate 24/7 support for their mission critical workloads residing in a collocated datacenter.
CWhen the customer wants to experience Platform as a Service (PaaS) that is inclusive of technology, Support, metering and management.
DWhen the customer wants to experience next generation technology not yet released for public consumption.
A customer acquired Gen10 Plus servers through HPE GreenLake last year. They want to add HPE GreenLake for Block Storage to their GreenLake footprint. When they ask for a quote, you explain that this process can be initiated from their HPE GreenLake Central instance through a wizard-driven application.
What information must you collect for the wizard?
Choose two
AReserved capacity
BHPE customer ID
CSite contact info
DDatacenter address
ESubscription term
A customer requires a compute solution. Its aging data center can provide only 5 kW per rack, which is less than the 15 kW needed for the planned solution.
Which changes could you recommend to meet the requirement while preserving the planned solution’s performance level?
Choose two
ADesign the solution with non-redundant power supplies.
BUse BMC tools to cap the power consumption of each server at 33%.
CSpread the infrastructure across additional racks.
DHost the compute solution with a colocation provider.
EConvert the solution to HPE GreenLake pay-per-use.
A customer has requested a new storage platform for its mission-critical Microsoft SQL environment. The environment has exceeded the capacity of its current platform and is expected to grow further as new applications come online. You recommend HPE Alletra 9000.
Which HPE Alletra 9000 business values should you discuss as part of the recommendation?
Choose two
Adistributed parallel access
B100% uptime guarantee
CEnterprise scalability and performance
Dmainframe and open systems support
Ebuilt-in continuous data protection
Match each Data Center Bridging (DCB) protocol component to its description.
Drag & Drop
APP
ETS
DCBX
PFC
Communicates key parameters between DCB-capable devices.
Enables control over how much bandwidth can be used over a conventional link.
Helps to ensure that Ethernet can provide the lossless frame delivery of FCoE.
Provides instructions to CNA about application-to-CoS mapping.
Which traditional use cases can HPE GreenLake for Block handle?
Choose two
AContainerized AI workload utilizing Microsoft Azure and an Apollo 4000.
BHighly secure, air-gapped NFS share from an MSA 2062.
CCollocated VMFS datastore mounted from an Alletra 9080 and protected by Zerto.
DMainframe volumes provided by HPE XP8 storage.
EOn-premises mission critical Oracle database hacked by an Alletra 6050.
A customer needs help modernizing its database infrastructure with a solution that can scale as its needs grow and enables its IT staff to focus on value-added activities.
Which benefit would the customer receive by selecting HPE GreenLake for Databases?
ACost savings with a community cloud operating model that supports sharing resources with other tenants.
BTime savings with a fully managed VDI solution hosted in their choice of AWS or Azure.
COrder prioritization with delivery and provisioning of new capacity in 7 days or fewer.
DOffload monitoring and modifying databases with HPE GreenLake management services.
A customer requires a managed private-cloud solution while retaining ownership for tax purposes.
Which delivery model should you recommend?
AHPE GreenLake for Virtual Desktop Infrastructure (VDI).
BHPE Financial Services lease with GreenLake management services.
CTraditional purchase with GreenLake management services.
DCustom HPE GreenLake solution based on a reference architecture.
Which protocol would you recommend for a dedicated, lossless fabric?
AInternet SCSI (iSCSI)
BFibre Channel (FCP)
CFibre Channel over Ethernet (FCoE)
DFibre Channel over IP (FCIP)
A customer is considering a new HPE Alletra 9060 to support its mission-critical database workloads.
The CFO is concerned about the cost of unused excess storage capacity intended for unforeseen future growth.
Which HPE GreenLake for Block Storage business value could help alleviate this concern?
AIt offers CapEx purchases so the client can depreciate the storage assets.
BIt sets the minimum capacity commitment level to the required capacity.
CIt provides storage capacity on an as-needed basis at a predetermined cost per GB.
DIt provides a fixed monthly cost, regardless of the storage consumption.