QuestionQ32

PowerScale Hardware Installation

What is the correct sequence of steps for installing a Dell PowerScale cluster using a Leaf-Spine topology?

Drag & Drop
Explanation

The switch operating-system version must be supported before fabric deployment. Build the physical fabric spine-first and then leaf switches, cable leaf-to-spine and leaf-to-node connections, establish the initial cluster with the four nodes on the first leaf switch, and then join the remaining nodes. Dell documents that PowerScale nodes attach to leaf switches and that leaf switches connect to spine switches.