QuestionQ74

Project Management Concepts

A PM is working with the IT department to identify staging-environment maintenance windows so that testing can be scheduled around those times. Which of the following processes is being described?

  • A Continuous deployment
  • B Customer notification
  • C Infrastructure change control
  • D Automation testing
Explanation

Infrastructure change control coordinates planned changes and maintenance activities in shared environments so dependent work, such as testing in a staging environment, can be scheduled to avoid disruption.