QuestionQ73

Project Management Concepts

A software engineer observes that the latest update to the reporting software contains many new features that were not specified in the requirements document. Which step should the engineer take next?

  • A Seek approval before continuing.
  • B Edit the requirements document.
  • C Disregard the update.
  • D Notify the users of the new features.
Explanation

Features outside the documented requirements are a scope change and require approval through the appropriate change-control process before work continues or the change is accepted.