For an upcoming project kickoff, a PM needs a way to show roles for major project activities. Which of the following would be the MOST useful option?

  • A Resource plan
  • B Organizational chart
  • C Project charter
  • D RACI chart
Explanation

A RACI chart assigns and communicates role involvement for each project activity by identifying who is Responsible, Accountable, Consulted, and Informed.