A project has recently completed user acceptance testing. Which action should the project manager perform first before closing the project?

Explanation

Formal validation of project deliverables confirms that they satisfy the approved requirements and acceptance criteria. This acceptance must be completed before closure activities such as documenting lessons learned, closing contracts, and releasing resources.