After identifying the appropriate maintenance window, which of the following should occur next in the operational infrastructure change process?
A rollback plan must be developed before implementation so the team knows exactly how to restore the prior state if the change fails or causes unexpected impact once the maintenance window is set. Notifying customers and validating checks come later in the change process, after the rollback contingency is documented.