QuestionQ43

Tools and Documentation

During a kickoff-meeting agenda, time is allocated to complete a document that identifies every project member, the members’ roles and task responsibilities, the milestones, and the key decisions. In which of the following should this information be documented?

  • A TOR
  • B WBS
  • C RAM
  • D SOW
Explanation

A Terms of Reference (TOR) establishes the project’s participants, roles and responsibilities, milestones, and key decision-making arrangements.