During a project status meeting, an engineer reports that several assigned tasks were not completed on schedule. This will impact the overall project timeline. Which of the following is the best action for the project manager to take to reduce the likelihood that this occurs again?

Explanation

A task gap analysis identifies the underlying differences between planned and actual task performance, such as skill, resource, dependency, or expectation gaps. Addressing those gaps directly reduces the chance that assigned work will again be completed late.