QuestionQ381

Project Management Concepts

A project manager is assigned to a project that has contracts with vendors. Which actions should the project manager perform most often?

Choose two
  • A Update the issue log.
  • B Create a project charter.
  • C Validate the status report.
  • D Monitor performance.
  • E Approve deliverables.
  • F Baseline the project schedule.
Explanation

Managing contracted vendors requires ongoing monitoring of their performance against the contract and documenting issues that need resolution in the issue log. These are recurring control activities throughout vendor engagement.