QuestionQ380

Project Management Concepts

A project manager wants to track and maintain the project schedule, as well as assess whether work is advancing in line with the deadline. Which of the following should the project manager use to achieve this goal?

  • A Burndown chart
  • B Pareto chart
  • C Velocity chart
  • D Critical path diagram
Explanation

A critical path diagram identifies the dependent activities whose combined duration drives the project completion date. Monitoring those activities reveals whether schedule progress and any delays will affect the deadline.