QuestionQ32

VerifiedTools and Documentation

A customer requests changes to a product, and the CCB approves those changes. Which of the following should be updated first?

Explanation

The Statement of Work (SOW) defines the agreed scope, deliverables, and work to be performed. Approved changes to a product must be reflected in the SOW before updating related measures such as ROI or KPIs, or responsibility assignments such as a RACI.