A new project team began working three months ago. Its members are becoming more productive and feel comfortable asking for help with tasks. Which of the following describes the project team’s current stage?

Explanation

The norming stage is characterized by increased trust and collaboration among team members. As relationships and working practices stabilize, team members become more comfortable seeking help and productivity improves.