Project Management ConceptsA few weeks before the project is scheduled for completion, the client requests that a new feature be added to the product under development. The project manager analyzes the schedule and concludes that the feature can be implemented fairly easily without affecting the completion date. Which action should the project manager take FIRST?
- A Escalate the change to the CCB.
- B Review the requested change.
- C Document the change recommendations.
- D Validate the implementation of the requested change.