QuestionQ238

Tools and Documentation

Which of the following activities would require a team to remove a new package and retain the previous one during a smoke test?

  • A Rollback plan
  • B Downtime stage
  • C Maintenance window
  • D Validation checks
Explanation

A rollback plan defines the procedure for reverting a deployment when validation, including a smoke test, indicates that the newly deployed package is not acceptable.