QuestionQ237

Tools and Documentation

Given the following chart:

Question Image

Which option best describes the project’s status on Day 5?

  • A The sprint is complete.
  • B The project is ready for gate review.
  • C The project is on time.
  • D The project is behind schedule.
Explanation

On Day 5, the actual number of remaining tasks is higher than the planned trendline, meaning the team has completed less work than expected by that date. The project is behind schedule.