QuestionQ198
Project Management ConceptsWhich of the following represents a quantitative key performance indicator?
- A The project sponsor ranked the graphics of an application as four out of five.
- B The project implements the application in ten different geographical regions.
- C The workers complete tasks on average 25% faster using a new application.
- D The use of a multimedia interface appeals more to users under the age of 21.