Project Management Concepts

A project manager receives differing functional requests from three individual stakeholders. The project manager can have every party make some concessions to reach a reasonable solution. Which of the following outcomes is most likely?

  • A Too much time might be spent generating project delays.
  • B The project manager might be seen as weak.
  • C The number of change requests throughout the project might be reduced.
  • D Some stakeholders might not be completely satisfied.
Explanation

Compromising requires each party to give up part of its preferred outcome to reach an acceptable resolution; therefore, some stakeholders may not be fully satisfied.