QuestionQ168

Project Management Concepts

A project team has not reached a final agreement on critical project deliverables, despite a clearly defined scope of work and several discussions about issues arising during the project. Which technique is the project manager most likely to use to resolve the matter?

  • A Collaborating
  • B Compromising
  • C Forcing
  • D Smoothing
Explanation

Collaborating addresses the underlying concerns of all parties, integrates their perspectives, and aims for consensus on a solution. It is the most suitable approach for resolving disagreement about critical deliverables when a durable agreement is needed.