During the planning phase, a PM has defined the tasks, durations, resources, and costs. Which of the following is the next step in the process?

  • A Update the work breakdown structure.
  • B Review the backlog.
  • C Seek baseline approval.
  • D Establish the resource pool.
Explanation

Once the work, duration, resource, and cost estimates have been defined, the resulting project plan and its schedule and cost baselines should be submitted for stakeholder or sponsor approval before execution proceeds.