An organization is planning to deploy new software. The project manager compiles a list of roles that will participate in various phases of the deployment life cycle. Which of the following should the project manager use to track those roles?

  • A CMDB
  • B Recall tree
  • C ITIL
  • D RACI matrix
Explanation

A RACI matrix maps project activities or phases to the people or roles that are Responsible, Accountable, Consulted, and Informed, providing a clear record of role involvement and responsibility throughout a deployment life cycle.