QuestionQ30

VerifiedSecurity Program Management and Oversight

An organization is planning to deploy new software. The project manager compiles a list of roles that will participate in various phases of the deployment life cycle. Which of the following should the project manager use to track those roles?

Explanation

A RACI matrix maps project activities or phases to the people or roles that are Responsible, Accountable, Consulted, and Informed, providing a clear record of role involvement and responsibility throughout a deployment life cycle.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!