QuestionQ9

Intake and planning

A project manager needs to identify the date on which a task is likely to finish, based on the task’s current progress and that of its predecessors, irrespective of any applied task constraints.

Which date type should the project manager use?

  • A Estimated Date
  • B Projected Date
  • C Planned Date
Explanation

A Projected Date forecasts when a task is likely to finish from its current progress and predecessor status, independently of task constraints.