QuestionQ8

Intake and planning

A video designer is spending an excessive number of hours on a Project involving the editing of a TV commercial. These tasks are preventing the designer from completing other assigned work. After discussing the issue with the designer, the project manager determines that the additional hours for this Project are necessary and suspects that the hours budgeted for the video designer’s time on this Project were too low compared with the actual need. The project manager needs data to demonstrate the issue and potentially request additional resources for this Project so the designer can still meet commitments for other assigned work.

Which native Project tool is intended to show how the Planned Hours for the video designer on this Project differ from the Actual Hours spent on the Project?

  • A Utilization
  • B Workload Balancer
  • C Hours
Explanation

Adobe Workfront’s Utilization report displays Planned Hours and Actual Hours for included projects and summarizes actual logged hours by individual user or job role, enabling comparison of planned effort with time actually spent.

Learn more

Community Discussion

No comments yet. Be the first to start the discussion!