QuestionQ57
VerifiedIntake and planningTwo team members are assigned to a task that, based on its predecessor and task constraint, is expected to begin this Tuesday, but its Planned Start Date appears as this Friday.
Why might this be happening?
Two team members are assigned to a task that, based on its predecessor and task constraint, is expected to begin this Tuesday, but its Planned Start Date appears as this Friday.
Why might this be happening?