Two team members are assigned to a task that, based on its predecessor and task constraint, is expected to begin this Tuesday, but its Planned Start Date appears as this Friday.

Why might this be happening?

Explanation

When the project is configured to consider user time off in task durations, Adobe Workfront adjusts a task’s planned dates for time off recorded by the task’s Primary Assignee. That adjustment can move the Planned Start Date later even when the predecessor relationship and task constraint would otherwise place it on Tuesday.