QuestionQ56
VerifiedIntake and planningThe project’s second task must be finished within 48 hours and must start 5 business days after the first task is completed.
Which task settings should be configured to satisfy these requirements?
The project’s second task must be finished within 48 hours and must start 5 business days after the first task is completed.
Which task settings should be configured to satisfy these requirements?