QuestionQ56

VerifiedIntake and planning

The project’s second task must be finished within 48 hours and must start 5 business days after the first task is completed.

Which task settings should be configured to satisfy these requirements?

Explanation

Task duration controls the scheduled span of work; setting it to 2 days meets a 48-hour/two-business-day requirement. A Finish-to-Start dependency makes the second task start after the first task finishes, and a positive lag of 5 days delays that start by five business days. Planned Hours represents effort, not the required schedule duration.

Learn more