QuestionQ54

VerifiedIntake and planning

A stakeholder has identified a possible scheduling conflict on an active project. The conflict could delay the completion date by two weeks. The stakeholder wants to document this timeline risk.

Which action should the stakeholder take to record the risk?

Explanation

A risk is a potential event that could affect the project schedule, so it should be entered in the project risk record and categorized as a schedule risk. An issue records a problem that has already happened, while a task’s planned completion date is not a risk log.