QuestionQ53

VerifiedIntake and planning

The marketing team should start working on a task on September 23, complete it within 2 weeks, and spend approximately 10 hours during that time span to execute the deliverable.

Which task settings must be configured to meet these requirements?

Explanation

A Must Start On constraint fixes the task’s planned start date, Planned Hours represents the estimated work effort, and Duration represents the scheduled time span between planned start and completion. The planned start date should be September 23, with 10 Planned Hours and a Duration of 2 weeks.