QuestionQ37Verified/Intake and planningCopy linkReport a problemAsk AstroTutorSave questionWhich task date type can a project manager manually change?APlannedBEstimatedCProjectedShow AnswerAnswerExplanationPlanned Dates are defined for a task by the Project Owner and can be manually modified. Estimated and Projected Dates are calculated by Adobe Workfront and cannot be manually changed.Learn moreAdobe Workfront: Overview of Projected and Estimated DatesShow comments0Show commentsCommunity DiscussionNo comments yet. Be the first to start the discussion!