QuestionQ36

VerifiedIntake and planning

A project manager reviews an Incomplete Tasks report and sees several tasks listed even though they are marked 100% complete.

Which column can the project manager add to the view to determine why those tasks appear in the report?

Explanation

In Adobe Workfront, incomplete-task reporting is based on whether a task has a Complete or Closed status, or a custom status that equates with Complete. The Status field reveals whether a task marked 100% is still in a status that Workfront treats as incomplete, such as a pending-approval state.