QuestionQ26

Intake and planning

Because of a time-sensitive shift in priorities, a project's timeline must be adjusted.

What action should the Project Owner take before changing the task timeline to avoid sending notifications to the project team?

  • A Update the project status.
  • B Recalculate the project timeline.
  • C Update the project baseline.
Explanation

In Adobe Workfront, setting a project to the Planning status before changing its plan prevents notifications related to project changes, such as task assignments and timeline updates, from being sent automatically to the project team. A baseline records a schedule for comparison, while recalculation only updates timeline calculations.