QuestionQ26
Intake and planningBecause of a time-sensitive shift in priorities, a project's timeline must be adjusted.
What action should the Project Owner take before changing the task timeline to avoid sending notifications to the project team?
- A Update the project status.
- B Recalculate the project timeline.
- C Update the project baseline.