QuestionQ25

Execute

A creative team accesses its assigned work through a My Tasks list report. The team wants to easily identify any New tasks by highlighting them for visibility.

How can the project manager fulfill the team’s request?

Explanation

Adobe Workfront applies conditional formatting in a report or list view through Column Rules. A Column Rule can use task Progress Status as its condition and apply visual formatting to New tasks, making them stand out while retaining the full task list.