QuestionQ25

Execute

A creative team accesses its assigned work through a My Tasks list report. The team wants to easily identify any New tasks by highlighting them for visibility.

How can the project manager fulfill the team’s request?

  • A Schedule a daily automatic report delivery of the New tasks in the report to the team.
  • B Create a grouping for task Progress Status and use a custom color pie chart for visibility.
  • C Create a Filter that uses conditional formatting to display New tasks only.
  • D Create a View that uses Column Rules to format the New tasks for visibility.
Explanation

Adobe Workfront applies conditional formatting in a report or list view through Column Rules. A Column Rule can use task Progress Status as its condition and apply visual formatting to New tasks, making them stand out while retaining the full task list.