QuestionQ113

VerifiedIntroduction to Applying the ADM

During which part of the ADM cycle are building-block gaps associated with the work packages that will resolve those gaps?

Explanation

Phase E, Opportunities and Solutions, identifies work packages from the target architecture building blocks and associates the gaps with the work packages that will address them. Phase F subsequently prioritizes and sequences the work packages for implementation and migration planning.