QuestionQ31

VerifiedConcepts

Consider the following statements about the TOGAF ADM.

  1. When a phase begins, the preceding phase ends.
  2. All activities occur within an iterative cycle of ongoing architecture definition and realization.
  3. Outputs from an earlier phase can be changed in a later phase.
  4. Phase E finalizes the Implementation and Migration Plan.
  5. The Requirements Management phase is a continuous phase.

Which statements are correct?

Explanation

The TOGAF ADM is iterative, its earlier-phase outputs may be modified in subsequent phases, and Requirements Management is a continuous process applied throughout the ADM. Finalizing the Implementation and Migration Plan is an objective of Phase F (Migration Planning), not Phase E (Opportunities and Solutions).

Community Discussion

No comments yet. Be the first to start the discussion!