Complete the following sentence. In the TOGAF Architecture Content Framework, an artifact that comprises a list of things is called a _________________.
Abuilding blocks
Bmatrix
Ccatalog
Ddeliverable
Ediagram
Which of the following best describes the purpose of ADM Phase E?
ATo define the initial implementation plans
BTo define the scope, identifying stakeholders and obtaining approvals
CTo develop the Technology Architecture
DTo manage requirements throughout the ADM
ETo perform architectural oversight for the implementation
Which of the following forms part of Architecture Governance?
ACreating and maintaining the Statement of Architecture Work though out the ADM cycle.
BManaging Stakeholders and their requirements.
CInteracting with the CxO level on Enterprise Architecture.
DEnsuring compliance with internal and external standards and regulatory obligations.
Complete the statement. The Architecture Landscape is divided into three levels: Strategic, Segment, and ____________.
ABaseline
BCapability
CSolution
DTarget
ETransition
QuestionQ6
Part 1: The TOGAF Standard
0
Community Discussion
No comments yet. Be the first to start the discussion!
QuestionQ7
Part 1: The TOGAF Standard
QuestionQ8
Part 1: The TOGAF Standard
QuestionQ9
Part 2: Applying the TOGAF Standard
QuestionQ10
Part 1: The TOGAF Standard
QuestionQ11
Part 2: Applying the TOGAF Standard
QuestionQ12
Part 2: Applying the TOGAF Standard
QuestionQ13
Part 2: Applying the TOGAF Standard
QuestionQ14
Part 1: The TOGAF Standard
QuestionQ15
Part 1: The TOGAF Standard
QuestionQ16
Part 1: The TOGAF Standard
QuestionQ17
Part 1: The TOGAF Standard
QuestionQ18
Part 1: The TOGAF Standard
QuestionQ19
Part 2: Applying the TOGAF Standard
QuestionQ20
Part 1: The TOGAF Standard
QuestionQ21
Part 1: The TOGAF Standard
QuestionQ22
Part 1: The TOGAF Standard
QuestionQ23
Part 2: Applying the TOGAF Standard
QuestionQ24
Part 2: Applying the TOGAF Standard
QuestionQ25
Part 1: The TOGAF Standard
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Ad
Want a break from the ads?
Go ad-free and unlock Learn Mode, Exam Mode, AstroTutor AI and every premium tool — everything you need to walk in prepared, and confident.
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
Save question
0
Community Discussion
No comments yet. Be the first to start the discussion!
An association of companies has created a data model to share inventory and pricing information.
Which option best describes where this model fits within the Architecture Continuum?
AFoundation Architecture
BCommon Systems Architecture
CIndustry Architecture
DOrganization Specific Architecture
EProduct Line Architecture
Which of the following is considered a relevant architecture resource in ADM Phase D?
AGeneric data models relevant to the organization's industry sector
BExisting application models
CGeneric technology models relevant to the organization's industry sector
DExisting IT services
Complete the sentence: TOGAF covers the development of four architecture domains: Application, Business, Data, and ________.
ACapability
BSegment
CTechnology
DTransition
EVision
Refer to the Scenario.
The EA team leader has asked you to examine the preliminary Architecture Contracts and recommend the best approach to address the Chief Engineer’s concern.
Based on the TOGAF Standard, which of the following is the best answer?
AYou recommend that the Architecture Contracts be used to manage the architecture governance processes across the locations. You recommend deployment of monitoring tools to assess the performance of each completed battery pack at each location and develop change requirements if necessary. If a deviation from the contract is detected, the Architecture Board should allow the Architecture Contract to be modified meet the local needs. In such cases they should issue a new Request for Architecture Work to implement a modification to the Architecture Definition.
BFor changes undertaken by internal teams, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. If a contract is issued to a contractor, you recommend that it is a fully enforceable legal contract. If a deviation from the Architecture Contract is found, you recommend that the Architecture Board grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
CYou check the contracts ensuring that they address project objectives, effectiveness metrics, acceptance criteria, and risk management. Third-party contracts must be legally enforceable. You advise that there be a schedule of compliance reviews at key points in the implementation process. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the process to be customized for local needs.
DFor changes requested by an internal team, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to third-party contractors, you recommend that it is a fully enforceable legal contract. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
The TOGAF ADM uses version numbering to show the evolution of Baseline and Target Architecture Definitions. Which version number indicates a high-level outline of the architecture?
AVersion 0.1
BVersion 0.7
CVersion 1.0
DVersion 0.9
EVersion 0.5
What should be established through organizational structures, roles, responsibilities, skills, and processes to perform architectural activity effectively?
AAn EA repository
BAn Enterprise Architecture
CAn EA framework
DAn EA Capability
Refer to the Scenario.
You have been asked to recommend the most appropriate approach for addressing the Chief Engineer's concern.
Based on the TOGAF standard, Version 9.2, which of the following is the best answer?
AYou review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract. You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definition. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
BYou create an Architecture Contract to manage and govern the implementation and migration process at each location. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
CYou create an Architecture Contract to manage and govern the implementation and migration process. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contract. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization. You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
DYou use the Architecture Contracts to manage the architecture governance processes for the project across the locations. You deploy monitoring tools to assess the performance of each completed turbine at each location and develop change requirements if necessary. You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the ability to customize the process to meet their local needs. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.
In Phase G, which document establishes the link between the architecture organization and the implementation organization?
AArchitecture Contract
BArchitecture Landscape
CArchitecture Roadmap
DRequirements Impact Statement
ETransition Architecture
Complete the sentence: The Architecture Landscape is organized into levels: Strategic Architectures, _____________
ASegment Architectures, and Capability Architectures
BSolution Architectures, and Corporate Architectures
CGap Architectures, and Target Architectures
DTransitional Architectures, and Incremental Architectures
EBaseline Architectures, and To Be Architectures
Which of the following does TOGAF define as “the structure of components, their inter-relationships, and the principles guiding their design and evolution over time”?
AView
BArtifact
CModel
DDeliverable
EArchitecture
Complete the sentence: The Architecture Landscape is divided into three levels: Strategic Architectures, Segment Architectures, and _____________.
ABaseline Architectures
BCapability Architectures
CSolution Architectures
DTarget Architectures
ETransition Architectures
Complete the sentence: All of the following are components of the conceptual structure of the TOGAF Architecture Governance Framework, except ______.
AContent
BContext
CProcess Flow Control
DRepository
EVision
Which of the following most accurately describes TOGAF?
AAn abstract framework for the development of standards and processes for a business architecture
BA collection of components organized to accomplish a specific set of functions
CA process model, best practices and assets to aid production, use and maintenance of enterprise architectures
DA reference model containing taxonomy defining terminology for an enterprise architecture, together with an associated graphic
EA system development lifecycle method for software engineering
Which of the following activities is the responsibility of the Requirements Management Phase?
AAddressing requirements
BDisposal of resolved requirements
CGenerating requirements
DManaging the flow of requirements
EPrioritizing requirements
In which phase of the TOGAF ADM does the focus concern creating an Implementation and Migration Plan in cooperation with the portfolio and project managers?
APhase F
BPhase D
CPhase G
DPhase E
EPhase A
Which pair of the responses below best completes the sentence?
Architecture building blocks ____, whereas Solution Building blocks ____.
Aare assembled; are single function components
Bare single function components; are groups of architecture building blocks
Care reusable; are not reusable
Ddefine the architecture; provide the existing legacy system
Edefine functionality; define the implementation of functionality
According to TOGAF, which step in Phases B, C, and D takes place before the baseline or target architectures are developed?
AConduct formal stakeholder review
BCreate Architecture Definition Document
CDefine Roadmap components
DPerform gap analysis
ESelect reference models, viewpoints and tools
Which of the following statements best explains why the ADM should be adapted?
ATo align it closer to the business
BTo make the use more realistic
CTo move through the cycle faster
DTo suit the specific needs of the enterprise
If the current activity in Phase B is defining candidate roadmap components, what is the next activity?
ACreate Architecture Definition Document
BDevelop Target Architecture Description
CConduct formal stakeholder review
DResolve impacts across the Architecture Landscape
EDevelop Baseline Architecture
Which section of the TOGAF document defines taxonomies for classifying the outputs of architecture activity?
Community Discussion