QuestionQ42

VerifiedThe TOGAF Standard, Version 9.2

You are acting as the Lead Architect for the SPICE project team.

You have been asked to recommend an approach for identifying the work packages that will be included in the Transition Architecture(s).

Based on TOGAF 9, which of the following is the best answer?

Explanation

TOGAF 9 ADM Phase E identifies and classifies solutions for architecture gaps, groups related solutions into work packages, analyzes dependencies and implementation constraints, and organizes the packages into capability increments and Transition Architectures. The Architecture Definition Increments Table records those planned increments; clinical-trial schedules are a relevant dependency and rollout constraint.

Community Discussion

No comments yet. Be the first to start the discussion!