QuestionQ39

The TOGAF Standard, Version 9.2

You have been asked to recommend the next actions to prepare the final Implementation and Migration Plan.

Based on the TOGAF standard, which of the following is the best answer?

  • A You would apply the Business Value Assessment Technique to prioritize the implementation projects and project increments. The assessment should focus on return on investment and performance evaluation criteria that can be used to monitor the progress of the architecture transformation. You would confirm the Transition Architecture phases using an Architecture Definition Increments Table to list the projects. You would then document the lessons learned and generate the final plan.
  • B You would assess how the plan impacts the other frameworks in use in the organization. The plan should be coordinated with the business planning, portfolio/ project management and operations management frameworks. You would then assign a business value to each project, considering available resources and priorities for the projects. Finally, you would generate the Implementation and Migration Plan.
  • C You would conduct a series of Compliance Assessments to ensure that the implementation team is implementing the architecture according to the contract. The Compliance Assessment should verify that the implementation team is using the proper development methodology. It should include deployment of monitoring tools and ensure that performance targets are being met. If they are not met, then changes to performance requirements should be identified and updated in the Implementation and Migration Plan.
  • D You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle. This will ensure that the architecture remains relevant and responsive to the needs of the enterprise. You would then produce an Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You recommend that lessons learned be accepted by the Architecture Board as changes to the architecture without review.
Explanation

TOGAF Phase F finalizes the Implementation and Migration Plan by coordinating it with business planning, portfolio/project management, and operations management frameworks. It also assigns business value to work packages or projects and accounts for resource availability and priorities before completing the plan.

Learn more