QuestionQ39

VerifiedThe TOGAF Standard, Version 9.2

You have been asked to recommend the next actions to prepare the final Implementation and Migration Plan.

Based on the TOGAF standard, which of the following is the best answer?

Explanation

TOGAF Phase F finalizes the Implementation and Migration Plan by coordinating it with business planning, portfolio/project management, and operations management frameworks. It also assigns business value to work packages or projects and accounts for resource availability and priorities before completing the plan.