QuestionQ34
The TOGAF Standard, Version 9.2You have been asked to recommend an approach for identifying the work packages to be included in the Transition Architecture(s).
Based on the TOGAF standard, which of the following is the best answer?
- A You would document the factors impacting the Implementation and Migration Plan and group the gaps identified in the domain architecture gap analysis results. For each gap, you would identify a proposed solution and classify it as a new development, purchased solution, or based on an existing product. You would group similar solutions together to form work packages, and identify dependencies between the work packages factoring in the clinical trial schedules. Finally, you would regroup the packages into a set of Capability increments scheduled into a series of Transition Architectures.
- B You would use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap, you would classify whether the solution is either a new development, purchased solution, or based on an existing product. You would group the similar solutions together to define the work packages. You would then regroup the work packages into a Set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.
- C You would group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, you would then regroup the work packages to account for dependencies. You would sequence the work packages into the Capability Increments needed to achieve the Target Architecture. You would schedule the rollout one region at a time. Finally, you would document the progression of the Enterprise Architecture using a state evolution table.
- D You would determine the set of Solution Building Blocks required by identifying which need to be developed and which need to be procured. You would eliminate any duplicate building blocks, and then group the remaining Solution Building Blocks together to create the work packages using a CRUD matrix. You would then rank the work packages in terms of cost, and select the most cost-effective options for inclusion in a series of Transition Architectures. Finally, you would schedule a sequential roll out of the work packages across the geographic regions.