TOGAF ADM Phase F requires the Implementation and Migration Plan to be coordinated with the enterprise’s business-planning, portfolio/project-management, and operations-management frameworks. It also requires business value to be assigned to projects, taking priorities and available resources into account, before the detailed Implementation and Migration Plan is completed.