QuestionQ28

Project Management

Which property governs changes to cost and resource plans when the start date of a demand or project is changed?

  • A ‘Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change’.
  • B ‘Enable altering of planned date for task in WIP/Closed’.
  • C ‘Rollup project start date from tasks’.
  • D ‘Calculate ROI percentage based on a project's estimated cost and its net value’.
Explanation

The com.snc.project.date_change_cascade property updates the start dates of associated resource plans, cost plans, and benefit plans when a project or demand start date changes. Benefit-plan dates change only when the plan’s offset type is not None.