QuestionQ17

Resource Management

Which of the following can be used to calculate planned cost while creating a resource plan?

Choose two
  • A Default rate
  • B Demand rate
  • C Project rate
  • D Rate card
Explanation

Planned cost is derived by multiplying planned hours by an applicable hourly rate. The hourly rate can come from the rate configuration associated with the project or from a rate card; ServiceNow documentation describes this project-associated source as a rate model and also supports labor rate cards for resource-plan cost calculations.

Learn more